MT 200 Fairview Construction Project Update

The concrete paving phase of the project is complete. Crews are now moving on to the asphalt placement phase, which is expected to wrap up this week. Crews anticipate installing signs this week with striping scheduled to occur from Aug. 10-13. The traffic light at the 6th Street intersection is scheduled to be turned on Aug. 13.

Motorists are asked to remember that traffic on MT 200 (Ellery Ave) remains two-lane, two way while traveling on the new asphalt despite not having clearly defined lanes striped.

There are no additional traffic impacts planned for motorists traveling through the area and traffic will continue flowing. Traffic will remain reduced to two-lane, two-way traffic but the highway will remain open to traffic during construction. The traveling public is asked to prepare for occasional delays of up to 15 minutes and is reminded to slow down and watch for work crews and equipment in the construction zone.

 

Reader Comments(0)